The Lagos State Government has announced a detailed traffic diversion plan ahead of the long-awaited repairs of the Ogudu/Ifako Bridge, set to begin on Saturday, 28th June 2025, and extends to 110 days. The exercise will last till Wednesday, 15th October 2025.

The repair works, which was initially postponed, will now be executed in eight phases, split across both directions of the bridge.

The first to fourth phases, affect the inbound Alapere stretch, which will run from 28th June to 16th August (50 days).

The fifth to eighth phases, covering the inbound Oworonshoki section, will follow immediately, from 16th August to 5th October (51 days).

In a statement signed by the Commissioner for Transportation, Mr. Oluwaseun Osiyemi, motorists were advised to use designated alternative routes during the partial closures, which will be confined to a 50-metre segment before and after each active work zone.

“For phase one, motorists from Iyana Oworo are advised to go through Gbagada to connect Anthony, thereby accessing Ikorodu Road, which leads to multiple destinations with ease,” Osiyemi stated.

He further stated that one lane would remain open near the work area, to reduce traffic impact.

Assuring Lagosians of a well-coordinated operations , Osiyemi said,”We understand the inconveniences road repairs can bring, but the Ogudu/Ifako Bridge repairs are necessary to ensure long-term safety and structural integrity. Our goal is to keep traffic disruptions to the barest minimum.”

He also confirmed that officers of the Lagos State Traffic Management Authority (LASTMA) would be fully deployed along affected corridors to direct traffic and assist commuters.

“LASTMA personnel will be strategically stationed to manage flow, enforce diversions, and provide assistance as needed,” Osiyemi assured.

The commissioner appealed for understanding from road users, stating: “We implore motorists to remain patient during this period. The partial closure — limited to 50 metres before and after each repair site, is essential for the safe and efficient completion of the bridge maintenance, especially around the expansion joints.”

The repairs are being handled by the Lagos State Ministry of Works and Infrastructure (Office of Infrastructure).

The government said residents and road users were encouraged to stay updated through the official channels as work progresses on one of the city’s vital transport corridors.

By TheInterviewsNigeria

Publisher/Editor -in Chief with more than a decade of working in the media production industry, Our preoccupation is Development News and rooting for innovation locally and internationally. We are British trained Business English PRO. We edit manuscripts for book publication, translation(English/Yoruba/French). We cross your 't's' and dot your 'i's. We are also into speech draftsmanship and photography; Business reports, and proposals, with minimal cost. Meeting the deadline is our watchword. We would cover your Social /Public events with precision. The proof of the pudding is in the eating. Call-08144956897, 08057355037 E-mail- theinterviewsng@gmail.com, akintunde.idowu@gmail.com